In December 2024, specialists from the Mosmetrostroy subsidiary MMS International successfully completed work on the construction of tunnels at the facility “Bypassing the Shkotovo – Smolyaninovo section of the Far Eastern Railway.”

The Shkotovo – Smolyaninovo section is located on the electrified railway direction Ussuriysk – Nakhodka, located in the Primorsky Territory. This section of the railway line is one of the barrier areas; pushing locomotives were used to move freight trains, which reduced capacity.

To solve the problem, a project was developed to bypass the Shkotovo – Smolyaninovo section with the construction of an electrified double-track railway section 7.53 km long.

MMC International specialists built two single-track tunnels with a total length of 2870 meters, approaches to them with a length of 1500 meters, including two reinforced concrete bridges. In addition, a complex of engineering and technical security facilities was built at the port sites.

–Tunneling was carried out in difficult engineering and geological conditions. The mountain range along the tunneling route is represented by rocks, loam and clay with inclusions of layers and lenses of highly fractured water-saturated coal,” said Denis Chumachenko, director of MMC International. – During the excavation process, special methods of soil consolidation were used, including advanced fastening of the face with pipe screens. Drilling was carried out in three ledges, with counter faces from the East and West portals.

Despite the difficulties, construction was completed in a short time frame from 2021 to 2024, with high quality.

Mining work began in May 2022, and freight train traffic opened through the tunnels in December 2024.

For reference:

During construction, a colossal amount of work was carried out:

February 12 marks ten years since the founding of MMC International.

The company began operating in 2015 and has achieved significant success in the field of underground construction, implementing large-scale projects in Moscow, the Far East and the Republic of Serbia. Among the organization’s achievements: the reconstruction of the Kakhovskaya metro station, the modernization of the Vladivostok tunnel (the tunnel named after Comrade Stalin), the construction of tunnels to bypass the Shkotovo-Smolyaninovo section of the Far Eastern Railway.

Colleagues, new successes and achievements in all areas of work, good health, happiness and prosperity!